CTG Fujian 20MW Demonstration (Turbine Test Site)

Sub-500 MW but included as a significant China technology milestone. Fujian offshore test site. 26 MW and 35 MW prototypes already on roadmap.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2028
expected year of commercial operation
The developer says 2026; Hafrok expects 2028 — 2 years later.
Chance of delivery
≈97% estimated chance this project reaches commercial operation
Under Construction projects complete ≈97% of the time on Hafrok's record. Technical complexity and no offtake contract yet pull this one slightly below that.
COD outlook
If it completes, when — Hafrok’s probability by year (teal)
20%40%60%80%100% 2027: 10.0% (conditional on completion) 2028: 58.5% (conditional on completion) 2029: 26.6% (conditional on completion) 2030: 4.5% (conditional on completion) 2031: 0.5% (conditional on completion)2026now2027202858%EXPECTED202920302031 Developer-announced COD: 2026 ANNOUNCED 2026
COD probability by year, conditional on completion
YearProbability
202710.0%
2028 (expected)58.5%
202926.6%
20304.5%
20310.5%
How Hafrok got this date
1
Starting point: the last dated milestone
Construction start in 2026. From there Hafrok adds how long similar projects (in established offshore-wind markets) took to reach commercial operation, measured on projects that have delivered.
2
Typical timing
Starting point plus the typical remaining time gives a middle estimate of 2028; the faster quarter of similar projects would be done by 2027, the slower quarter not until 2029.
3
Result
Expected commercial operation 2028, likely range 2027–2029 (the middle half of outcomes for similar projects). The developer's announced date (2026) is earlier than similar projects have managed — Hafrok's own date is used and the difference is flagged above.
4
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
5
Chance of delivery — separate from timing
Start from the share of Under Construction projects that went on to complete — ≈97%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). Based on the measured record — all 257 construction starts with a final outcome reached operation — adjusted down for projects still mid-build and for legal-challenge risk. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈97%, which rates it Delivering on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2026’27’28Developer-announced COD: 2026 announced COD 2026View the source for Offshore constructionOffshore construction 13 Jan 2026 Commercial operation 2028 ·Hafrok expected
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.

Revenue & offtake the regime the project was built under

Offtake regime: Demonstration / not commercial
A built project sells its power under the contract or support regime it was financed with; it is not expected to bid into new government offtake rounds. Where the record does not yet name that regime, the row says so rather than guessing.

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation under way
no satellite count yet: this farm is outside the tracker’s coverage so far
Installation · on record
StageUnder Construction
Offshore constructionstarted 2026-01-13
Expected start of operation2026

Sources & verification

0/13 fields verified · rests on 4 sources · ◆ 1 document held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Trade press3
[2]
offshoreWIND.biz2026-01
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionSite rightsTurbinesUnit capacityTotal capacity+4 more
[3]
Global Energy Monitor2026-07-02
supportsoperatorCoordinates
[5]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown◆ China Installs World's First 20 MW Offsh…
supportsCommercial operationTurbinesUnit capacityTotal capacityWater depth+2 more