Hai Long 2
Located 45-70 km off Changhua County. Part of 1,022 MW Hai Long project (Hai Long 2 + Hai Long 3). SG 14-222 DD turbines (14 MW, upgradeable to 15 MW).
Status
Under Constructionlifecycle stage
Near certainHafrok delivery likelihood
Ownership
Location
Taiwan Strait
Technology
Capacity
518 MW ◆
Turbines
37 × 14 MW ◆
Model
Siemens Gamesa SG 14-222 DD ◆
Foundation
Jacket ◆
Site & conditions
Site rights
Seabed rights held ∴
Water depth
32–66 m ≈
Wind speed
10.9 m/s @ 150 m ≈
Revenue & grid
Offtake
PPA ◆
Grid
Secured · Jun 2025 ◆
Connection
Changhua County onshore substation (Taipower grid 161 kV) ◆
Schedule
FID
2023 ◆
COD · announced
2027 ◆
COD · Hafrok
for registered readers
Delivery outlook modelled by Hafrok · calibrated on delivered projects
Near certainHafrok's delivery likelihood for Hai Long 2
The developer says 2027. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
4 dated milestones on the spine, each with its source · 3 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 17 sources (7 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator5
[9]
Hai Long Offshore Wind2023
“Jan 2019 Hai Long 2A obtained the Establishment Permit from the Ministry of Economic Affairs. ... Dec 2019 Hai Long 2B and Hai Long 3 obtained the Establishment Permit from the Ministry of Economic Af…”
supportsConsentConsent granted
[11]
Northland Power2026-04◆ Northland power signs long term corporat…
“the 294-megawatt (MW) Hai Long 2A, the 224 MW Hai Long 2B, and the 504 MW Hai Long 3 with a combined gross capacity of 1,022 MW. ... The new 30-year agreement builds on the existing long-term partners…”
supportsTotal capacityMechanismDetail
[12]
Northland Power2025-06-12◆ Northland Power Achieves First Power on …
“Northland Power Inc. (TSX: NPI) today announced first power from its Hai Long Offshore Wind Project in Taiwan, marking successful energization of the project and connection to Taipower’s grid. ... The…”
supportsFirst powerFoundationStatusConnection point
[14]
Northland Power2026-08◆ Northland Power Reports Second Quarter 2…
“Northland continues to advance construction of the 1.0 GW Hai Long Project in Taiwan, with 71 of 73 turbines installed and 59 generating power. The project continues its wind turbine installation and …”
supportsCommercial operationCOD history
[15]
Northland Power2026-10-15◆ Northlands hai long offshore wind projec…
“today announced that all 73 turbines at Hai Long, its 1.0 GW offshore wind project in the Taiwan Strait, are now installed and generating power. ... The project remains on track for final permitting a…”
supportsoperatorowner
OEM1
[13]
Siemens Gamesa Renewable Energy2022-10-19◆ Siemens Gamesa and Hai Long light the wa…
“73 SG 14-222 DD offshore wind turbines are intended to be deployed. ... The SG 14-222 DD offshore wind turbines are planned to be installed 50 km off the coast of Changhua County. Each turbine will ha…”
supportsModelUnit capacity
Auction results2
[18]
Conventus Law2026-06-22◆ tw-selection-2018-tw-2018-bond
Taiwan 2018 grid allocation: Stage-1 NT$4m/MW + Stage-2 NT$2m/MW performance bond; establishment permit before end-2019
supportsFeed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Selection (遴選)
[19]
Conventus Law2026-06-22◆ tw-auction-2018-tw-2018-bond
Taiwan 2018 grid allocation: Stage-1 NT$4m/MW + Stage-2 NT$2m/MW performance bond; establishment permit before end-2019
supportsFeed-in tariff · Taiwan 2018 Offshore Wind Capacity Allocation — Competitive Auction (競標)
Trade press8
[4]
[5]
[6]
Power Technology2023
Press report — cited, not quoted; read it at the source link.
supportsFinal investment decision
[7]
offshoreWIND.biz2024-04-12
Press report — cited, not quoted; read it at the source link.
supportsOffshore constructionSite rightsFoundation
[8]
Northland Power (GlobeNewswire)2026-05
“51 out of 73 turbines now installed and 32 turbines generating power ... The project is on track for commercial operations in 2027, with overall costs aligned with original expectations.”
supportsCommercial operation
[10]
[16]
offshoreWIND.biz2026-08-12◆ Hai Long Secures Financing with 11 New B…
Press report — cited, not quoted; read it at the source link.
supportsTurbines
[17]
offshoreWIND.biz2025-06-12◆ 1 GW Hai Long Offshore Wind Project Deli…
Press report — cited, not quoted; read it at the source link.
supportsStatusConnection point
Unverified import1
[1]
Northland Power2025-06-12
“Northland Power Inc. (TSX: NPI) today announced first power from its Hai Long Offshore Wind Project in Taiwan”
supportsFirst powerWater depthCoordinates