Nederwiek I-B

Northern part of Nederwiek I area. Originally combined with I-A as single 2 GW site, split September 2024.

Status
Early Developmentlifecycle stage
ProspectiveHafrok completion outlook
Ownership
Location
Netherlands
North Sea
Technology
Capacity 1,000 MW 
Turbines
Foundation
Site & conditions
Site rights State-designated Nederwiek I-B / II / III (bundled) 
Water depth 25–27 m  Distance from shore 95 km  Wind speed 10.1 m/s @ 150 m 
Revenue & grid
Offtake
Grid No agreement  Connection Shared TenneT offshore substation platform with Nederwiek I-A; … 
Schedule
FID Not taken
COD · announced 2031 
COD · Hafrok 2033 expected

Delivery outlook modelled by Hafrok · calibrated on delivered projects

2033
expected year of commercial operation
The developer says 2031; Hafrok expects 2033 — 2 years later.
Chance of delivery
≈62% estimated chance this project reaches commercial operation
Early Development projects complete ≈61% of the time on Hafrok's record. A secured offtake contract lifts this one slightly; its size and technical complexity pull a little the other way.
COD outlook
If it completes, when — Hafrok’s probability by year (teal) · the developer’s COD guidance, by date stated (ink)
20%40%60%80%100% 2032: 14.1% (conditional on completion) 2033: 28.0% (conditional on completion) 2034: 22.7% (conditional on completion) 2035: 14.6% (conditional on completion) 2036: 8.7% (conditional on completion) 2037: 5.1% (conditional on completion) 2038: 3.1% (conditional on completion) 2039: 1.8% (conditional on completion) 2040: 1.1% (conditional on completion) 2041: 0.7% (conditional on completion)2026now2028203020312032203328%EXPECTED2034203620382040 Developer-announced COD: 2031 ANNOUNCED 2031developer cod guidance2026-04-15: the developer guided 20302026-042030 2026-06-16: the developer guided 2031 — source [3] — click for it2026-062031 [3]
COD probability by year, conditional on completion
YearProbability
203214.1%
2033 (expected)28.0%
203422.7%
203514.6%
20368.7%
20375.1%
20383.1%
20391.8%
20401.1%
20410.7%
Developer COD guidance, by the date it was stated
StatedAnnounced COD
2026-04-152030
2026-06-162031
How Hafrok got this date
1
No dated milestone yet
Nothing is consented or financed with a date, so the estimate starts from today (2026), adds the time similar projects (in established offshore-wind markets) took from consent to operation, plus an allowance for obtaining consent.
2
Earliest credible date
Typical consent-to-operation time plus allowances means commercial operation before 2033 is not credible.
3
Still needs an offtake award: NL-IJMUIDEN-VER-GAMMA-A
The project has no offtake contract yet. The next visible auction is around 2026 Q4; winners typically reach final investment decision about 2 years after an award (2028 Q4), then build time on top gives 2031 Q4. The milestone timing is already later than that, so it stands.
4
Result
Expected commercial operation 2033, likely range 2033–2039 (the middle half of outcomes for similar projects). With no milestone to build from, the earliest credible date is the estimate, with a deliberately wide range.
5
Year-by-year chart
The bars spread that estimate across years using how similar projects actually slipped against their dates — more often late than early, which is why the bars lean right.
6
Chance of delivery — separate from timing
Start from the share of Early Development projects that went on to complete — ≈61%, measured on Hafrok's record of delivered and abandoned projects, with an allowance held back where that record cannot yet speak (projects still unresolved, changed market conditions). About three in four early-stage projects with a final outcome went on to operate — a record from an easier era. Most of today's early pipeline is still unresolved, so the estimate discounts it. Then adjust for this project's own evidence — offtake, market, size, technical complexity — to ≈62%, which rates it Prospective on Hafrok's four-step delivery scale (Delivering · Expected · Prospective · Fragile).

Project timeline verified milestones only — each date carries its provenance mark

2027’28’29’30’31’32’33Developer-announced COD: 2031 announced COD 2031View the source for Consent appliedConsent applied 17 Jul 2026 Commercial operation 2033 ·Hafrok expected
Dashed tick marks today (9 Sep 2026). The ▲ below the spine is the developer-announced COD.
Announced COD: slipped so far +1.0 yr (first announced 2030) · the full guidance history is in the delivery chart above

Revenue & offtake route to market — open

No offtake secured — route to market open

No tender held. Nederwiek I-A produced zero bids Oct 2025; I-B tender postponed pending K13-A aviation safety resolution.

The routes describe what exists in this market — not a prediction of which the project will take. Timing math for the auction gate lives in the delivery outlook above.
Next visible round · from the auction calendar
Nederwiek I-B / II / III (bundled)
expected — · planned · the round names this project
indicative

Installation how the build is going · from satellite counts and Hafrok’s registers

Installation not started
nothing to count yet: the satellite tracker begins when offshore construction does
Installation · on record
StageEarly Development
Offshore constructionnot started
Expected start of operation2031
Grid connection
from Hafrok’s substation, converter and cable registers
Offshore platforms · 1
HVDC systemNederwiek 1·2000 MW · ±525 kV · ordered, expected 2030
Export & onshore
Export cableNederwiek 1 Export Cable·HVDC subsea · 217 km · Prysmian · ordered · to Sloegebied, Zeeland
Onshore connectionBorssele Converter Station (Nederwiek 1)·525 DC / 380 AC kV · under construction · also serves Nederwiek I-A
Converter supplierHitachi Energy·Nederwiek 1 · TBD (originally Petrofac EPCI, now L&T) · for TenneT
Grid connection · ready in time?
when each part of the grid connection is due, against the start date the developer states (black line) and the year Hafrok expects (teal band) · a bar spans the whole year, quarter or month the source gives
installed or in serviceexpected deliveryearlier date that was later moved
20262027202820292030203120322033Hafrok expects the farm to start in 2033developer’s stated start 2031nowNederwiek 1Nederwiek 1expected 2030expected 2030Borssele Converter Station (Nederwiek 1)Borssele Converter Station (Neder…expected 2030expected 2030Nederwiek 1 Export CableNederwiek 1 Export Cableexpected 2030expected 2030

Sources & verification

4/14 fields verified · rests on 10 sources (4 primary) · ◆ 5 documents held
VerifiedModelledSourcedInferredConventionUnverifiedNo source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator3
[1]
RVO (Netherlands Enterprise Agency)2025-10◆ Permit for wind farm Nederwiek I-A | RVO…
"NW I-B will also be connected to the platform later. This means that two 1 GW wind farms will connect to one platform." Located approximately 95 km off the west coast of Texel in the North Sea. No ap…
supportsTotal capacityStatusConnection pointDistance from shore
[5]
RVO (Netherlands Enterprise Agency)2026◆ RVO IJmuiden Ver Gamma-A tender opens 20…
“Only IJmuiden Ver Site Gamma-A included in the September 2026 tender. RVO notes "the Ministry of Climate Policy and Green Growth will decide whether to launch a second permit round for another one GW …”
supportsBackgroundStatus note
[8]
RVO — Bureau Energieprojecten (energietransitie.nl)2026-08-23◆ Dutch Bureau Energieprojecten register (…
“Listing row "Wind op zee - Nederwiek (zuid) kavel I-B" (key wind-op-zee-nederwiek-zuid-kavel-i-b); offshore docket page text hash 32cfb1805f116176… (7198 chars). Listing row "Net op zee - Nederwiek 1"…”
supportsRegister entry
Operator1
[9]
Rijksdienst voor Ondernemend Nederland (energietransitie.nl)2026-09-08◆ Wind op zee - Nederwiek (zuid) kavel I-B…
“Van vrijdag 17 juli tot en met donderdag 27 augustus 2026 lagen het ontwerp kavelbesluit en milieueffectrapport ter inzage. In die periode was het mogelijk om een zienswijze (reactie) in te dienen. De…”
supportsConsentConsent applied
Auction pipeline1
[10]
RVO2026◆ rvo-roadmap-2026
RVO roadmap — Nederwiek I-B grouped with Nederwiek II + III after the I-A failure; no firm tender year.
supportsNederwiek I-B / II / III (bundled)
Trade press5
[2]
Offshore Wind Biz2024-11-21
Press report — cited, not quoted; read it at the source link.
supportsBackgroundStatus note
[3]
Offshore Wind Biz2024-09-03
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationCOD historyTotal capacityDistance from shoreCoordinates
[4]
WindpowerNL2025-10-31
Press report — cited, not quoted; read it at the source link.
supportsDetailOfftake history
[6]
GEBCO Compilation Group2020
supportsWater depth
[7]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed