Kitakyushu Hibikinada Offshore Wind Farm

Located off Kitakyushu, Fukuoka Prefecture. Hibiki Wind Energy consortium.

Status
Operationallifecycle stage
Ownership
HWHibiki Wind Energy Co., Ltd. (ひびきウインドエナジー株式会社) — 100% ◇
JEJ-Power (Electric Power Development) — 40% ◆
KMKyuden Mirai Energy — 30% ◆
HOHokutaku — 10% ◆
SGSaibu Gas — 10% ◆
KRKRAFTIA — 10% ◆
Location
Japan
Sea of Japan (East Sea)
Technology
Capacity 220 MW ◆ Turbines 25 × 9.5 MW ◆ Model Vestas V174 9-5 ◆
Foundation —
Site & conditions
Site rights Seabed rights held ∴
Origination Kitakyushu Hibikinada offshore wind operator kobo (port-waters public solicitation) · 2017 ·
Water depth 8–20 m ≈ Wind speed 7.4 m/s @ 150 m ≈
Revenue & grid
Offtake FiT ◆ Grid Not recorded ◇ Connection Grid connection secured ◇
Schedule
FID 1 Mar 2023 ◆ COD 2 Mar 2026 ◆

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

5 dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the FiT contract's terms · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 14 sources (9 primary) · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[10]
Fukuoka Prefecture (福岡県)2021-12-22
“北九州響灘洋上ウィンドファーム(仮称) ... (補正済み)評価書の送付日 令和3年12月22日 ... (補正済み)評価書の縦覧期間 令和3年12月22日から令和4年1月27日まで [Translation: (corrected) environmental assessment statement (評価書) for the Kitakyushu Hibikinada Offshore Wi…”
supportsConsentConsent granted
Operator6
[2]
Saibu Gas Co., Ltd. (joint press release of the five consortium members)2017-04-17
“九電みらいエナジー株式会社、電源開発株式会社、株式会社北拓、西部ガス株式会社及び株式会社九電工からなるコンソーシアム(以下、「本コンソーシアム」)は、北九州市が実施した「響灘洋上風力発電施設の設置・運営事業者」の公募において、本年2月に占用予定者(優先交渉者)として選定されました。[…]SPC(特別目的会社)である「ひびきウインドエナジー株式会社」(以下、「ひびきウインドエナジー」)を設立します …”
supports↳ parent
[3]
J-POWER (Electric Power Development Co., Ltd.)2026-03-02◆ 北九州響灘洋上ウインドファーム 営業運転開始
“電源開発株式会社[…]が出資参画する北九州響灘洋上ウインドファームが本日営業運転を開始しました。[…]その後、ひびきウインドエナジー株式会社を通じて調査・準備を進め、2023年3月より建設工事に着手したものです。[…]ひびきウインドエナジー株式会社の概要 株主 九電みらいエナジー(株)、電源開発(株)、北拓(株)、西部瓦斯(株)、(株)クラフティア [Translation: the Kitaky…”
supportsConstruction startFirst powerCommercial operationTotal capacity
[9]
Mizuho Financial Group2023
“Mizuho Bank, Ltd. ("Mizuho", President & CEO: Masahiko Kato), MUFG Bank, Ltd. ("MUFG Bank", President & CEO: Junichi Hanzawa), and the Development Bank of Japan, Inc. ("DBJ", President & CEO: Seiji Ji…”
supportsFinal investment decision
[12]
J-POWER (Electric Power Development Co., Ltd.)2026-03-02◆ Kitakyushu Hibikinada Offshore Wind Farm…
“Electric Power Development Co., Ltd. (J-POWER) announces that the Kitakyushu Hibikinada Offshore Wind Farm project in which it is a participant has commenced commercial operation today... The wind far…”
supportsFirst powerCommercial operationTurbinesTotal capacity
[13]
J-POWER (Electric Power Development Co., Ltd.)2026-07-31◆ J-POWER FY2026 1Q earnings presentation
"Latest Status of Our Initiatives (As of June 30, 2026) ... Offshore Wind: Started commercial operation of 'Kitakyushu Hibikinada Offshore Wind Power Project'." A same-origin RECONFIRMATION four month…
supportsCommercial operation
[15]
Agency for Natural Resources and Energy, METI (資源エネルギー庁)2026-08-31◆ 再生可能エネルギー事業計画認定情報 公表用ウェブサイト — 40 福岡県 (20…
“UZ98009H40 | ひびきウインドエナジー株式会社 | 三根 浩二 | 福岡県北九州市若松区響町1‐122‐16 | 093-981-4362 | 洋上風力 | 160000 | 福岡県北九州市若松区柳崎町 北九州市港湾区域内水域等の指定された区域(西部地区) | 1 | - | 43917 | - | 2026年3月 | - | - | - | - | 2046年2月”
supportsMechanismDetail
OEM1
[14]
Vestas Wind Systems A/S2023-04-25
“Singapore, 25 April 2023 — Vestas has secured a 238 MW order from Hibiki Wind Energy for the Kitakyushu-Hibikinada Offshore Wind Farm Project located off the coast of Kitakyushu city, Fukuoka prefectu…”
supportsTurbinesModelUnit capacity
Trade press5
[5]
Japan Energy Hub2025
Press report — cited, not quoted; read it at the source link.
supportsoperator
[6]
Global Energy Monitor (GEM.wiki)2026-07-02
supportsCoordinates
[7]
GEBCO Compilation Group2020
supportsWater depth
[8]
offshoreWIND.biz2026-03-04
Press report — cited, not quoted; read it at the source link.
supportsCommercial operationTotal capacityStatusConnection point
[11]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Unverified import1
[1]
unknown
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityWater depthCoordinates
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.