Goto Floating Offshore Wind Farm

Located 7-11km offshore Kabashima Island, Goto City, Nagasaki Prefecture. First project to COD under Marine Renewable Energy Act.

Status
Operationallifecycle stage
Ownership
TCToda Corporation — 16.67% ◆
ERENEOS Renewable Energy — 16.67% ◆
OGOsaka Gas — 16.67% ◆
ICINPEX Corporation — 16.67% ◆
KEKansai Electric Power — 16.67% ◆
CEChubu Electric Power — 16.65% ◆
Location
Japan
East China Sea
Technology
Capacity 17 MW ◇ Turbines 8 × 2.1 MW ◆ Model Hitachi Htw 2-1 ◇
Foundation —
Site & conditions
Site rights Seabed rights held ∴
Origination Goto City (Nagasaki) Floating Offshore Wind Solicitation · 2021 ·
Water depth 11–20 m ≈
Revenue & grid
Offtake FiT ◆ Grid Not recorded ◇ Connection Grid connection secured ◇
Schedule
FID Taken · date not recorded ∴ COD 2026-Q1 ◇

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

4 dated milestones on the spine, each with its source · 1 recorded ownership deal from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 10 sources (3 primary) · ◆ 3 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator3
[5]
Toda Corporation2022-04-26
“本日、経済産業省及び国土交通省より、再エネ海域利用法に基づき建設する洋上風力発電所として、国内で初めて公募占用計画の認定を受けました。”
supportsConsentConsent granted
[6]
Chubu Electric Power2026-01-05
“2026年1月5日より開始したことをお知らせいたします ... 発電した電気は、エネルギーの地産地消の観点から、地域の小売電気事業者に優先して供給することとしています”
supportsFinal investment decisionFirst powerCommercial operation
[7]
Toda Corporation2026-01-05
“浮体式洋上風力発電設備 16.8MW(=2.1MW機×8基)(全長176.1m、ローター径80m)”
supportsTurbinesUnit capacity
Auction results1
[10]
Aquilo Energy / EEAS2026-06-22◆ jp-goto-floating-2021-jp-tenders-study
Japanese offshore-wind tenders study: 30-yr occupancy permit, scheduled operation <=8 years after Occupancy Plan certification
supportsTender award · Goto City (Nagasaki) Floating Offshore Wind Solicitation
Trade press5
[2]
offshoreWIND.biz2026-01◆ Japan's First Commercial Floating Wind F…
Press report — cited, not quoted; read it at the source link.
supportsoperatorownerMechanismDetail
[3]
GEBCO Compilation Group2020
supportsWater depth
[4]
offshoreWIND.biz2026
Press report — cited, not quoted; read it at the source link.
supportsOnshore constructionCommercial operationTotal capacityStatusConnection point
[8]
Nikkei2026-01
Press report — cited, not quoted; read it at the source link.
supportsModel
[9]
WindJournal2026
“日立製作所製の風車を据え付けている...出力2100kWの風車を8基設置し、総出力は1万6800kWである”
supportsModel
Unverified import1
[1]
unknown◆ Japan's First Commercial Floating Wind F…
Press report — cited, not quoted; read it at the source link.
supportsTotal capacityWater depth
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.