Alexandroupolis Offshore Wind Farm
Would be Greece's first offshore wind farm. Located south of Alexandroupolis coastline (Evros regional unit) and north of Samothrace island in the Thracian Sea.
Status
Proposedlifecycle stage
Ownership
TMTERNA Energy (Masdar) — 50% ◆
MOMotor Oil Renewable Energy — 50% ◆
Location
Thracian Sea
Technology
Capacity
400 MW ◇
Turbines
—
Foundation
—
Site & conditions
Site rights
Exploration right Exploration permit · HEREMA · 2023-11 ◆
Water depth
26–32 m ≈
Wind speed
7.5 m/s @ 150 m ≈
Revenue & grid
Offtake
—
Grid
No agreement ◇
Schedule
FID
Not taken
COD · developer
2030 announced ◇
Delivery outlook not forecast
We don't put a delivery estimate on this project yet. No authority has granted rights to this site, so there is nothing to date a schedule from. That changes the moment the seabed is awarded, a consent application is filed, or the project is named in an auction.
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
the dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 9 sources (1 primary) · ◆ 5 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator2
[2]
[8]
HEREMA (Hellenic Hydrocarbons and Energy Resources Management Company)2023-11-15◆ Issuance of the first 2 research licence…
“and Energy Resources Management Company (HEREMA S.A.) hereby announces that the first exploration licenses for Pilot Offshore Wind Farms have been officially awarded to the companies “AIOLIKI PROVATA …”
supportsSite rights
Auction pipeline1
[9]
HEREMA (Greece)2026◆ herema-offshore
HEREMA — first Organised Offshore Wind Development Areas ~1.9 GW; flexible CfD; auctions indicatively 2026-27.
supportsGreece first offshore wind auction (HEREMA)
Trade press6
[1]
[3]
HEREMA (Hellenic Hydrocarbons and Energy Resources Management Company)2023-11-15◆ Issuance of the first 2 research license…
“HEREMA issued exploration/research licenses valid for 3 years to AIOLIKI PROVATA TRAIANOUPOLEOS M.A.E. (subsidiary of TERNA ENERGY) and THRAKIKI AIOLIKI 1 S.A. (subsidiary of Copelouzos Group) for the…”
supportsConsentCoordinates
[4]
[5]
offshoreWIND.biz2025-01◆ Motor Oil and Masdar's Terna Energy Join…
Press report — cited, not quoted; read it at the source link.
supportsoperatordeveloper
[6]
[7]