Eoliennes Mediterranee Grand Large (Golfe de Fos)
AO6 Round 6 project. Second Mediterranean floating wind site under AO6. Sixth offshore wind project won by EDF in France.
Status
Advanced Developmentlifecycle stage
LikelyHafrok delivery likelihood
Ownership
Location
Mediterranean Sea
Technology
Capacity
250 MW ◆
Turbines
—
Foundation
Floating ◆
Site & conditions
Site rights
Seabed rights held ∴
Origination
France Offshore Wind AO6 (Mediterranean floating) · 2024 ·
Water depth
72–125 m ≈
Distance from shore
25 km ◆
Wind speed
9.9 m/s @ 150 m ≈
Revenue & grid
Offtake
CfD · €85.9/MWh ◆
Grid
Offered · Sep 2025 ◇
Connection
RTE offshore AC substation (Eiffage/Smulders EPCIC contract, … ◇
Schedule
FID
Not taken
COD · announced
2032 ◆
COD · Hafrok
for registered readers
Delivery outlook modelled by Hafrok · calibrated on delivered projects
LikelyHafrok's delivery likelihood for Eoliennes Mediterranee Grand Large (Golfe de Fos)
The developer says 2032. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
the dated milestones on the spine, each with its source · 2 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 15 sources (9 primary) · ◆ 9 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[12]
Préfecture de la région Provence-Alpes-Côte d'Azur2026-10◆ Parc éolien flottant Golfe de Fos 1 (fic…
“La société Éoliennes Méditerranée Grand Large (regroupant EDF Power Solutions et Maple Power) a été désignée lauréate pour ce projet de parc éolien flottant d'environ 19 éoliennes. RTE, gestionnaire d…”
supportsConsentCommercial operation
Operator9
[1]
Ministère de l'Économie et des Finances (French Government)2024-12-27◆ Construction et l’exploitation de deux p…
“Construction et l’exploitation de deux parcs éoliens en mer flottants : les deux lauréats de l’appel d’offres désignés ... Le ministre chargé de l’Industrie et de l’Énergie présente les deux projets r…”
supportsTotal capacityFoundationMechanismDetailDistance from shore
[2]
EDF Renewables2024-12-27◆ EDF Renouvelables et Maple Power remport…
“EDF Renouvelables and Maple Power have been selected by the Ministry of Industry and Energy to design, build and operate the Méditerranée Grand Large floating offshore wind farm of approximately 250 M…”
supportsTotal capacityDistance from shore
[3]
BW Ideol2024-12-27
“BW Ideol has been the consortium's technology partner since 2022, designing and manufacturing concrete floating foundations for the project.”
supportsFoundation
[4]
BW Ideol2025-11-26◆ BW Ideol Projects Company becomes a shar…
“BW Ideol Projects Company, a subsidiary of BW Ideol and ADEME Investissement dedicated to the development of floating offshore wind projects, has taken a minority equity stake (15%) in Eoliennes Médit…”
supportsStatus note
[6]
EDF Power Solutions2025-11
“BW Ideol Projects Company, a subsidiary of BW Ideol and ADEME Investissement dedicated to the development of floating offshore wind projects, has taken a minority equity stake ... 15% equity investmen…”
supportsoperatorowner
[10]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-08-25◆ French Eoliennes en mer register (DGEC),…
“Register node 809 (node--type-project) at /facades-maritimes-en-france/facade-mediterranee/projets-en-mediterranee/Golfe-Fos/Golfe-fos-1 — title 'Golfe de Fos 1'; page text 13540 chars, hash 06b6f2ea1…”
supportsRegister entry
[11]
Eoliennes Méditerranée Grand Large (project company)2026-10◆ Parc éolien en mer flottant Méditerranée…
“Le parc éolien en mer flottant Méditerranée Grand Large sera situé à plus de 25 km de la côte, dans le golfe de Fos. Composé d’un maximum de 19 éoliennes, il produira pour une puissance installée comp…”
supportsCommercial operationCOD historyFoundation
[13]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-10◆ Golfe de Fos 1
“Tarif d'achat de l'électricité produite* 85,90 €/MWh ... hors indexation ... 2028 : Date prévue de démarrage des travaux du parc ... 2031 : Date prévue de mise en service du parc”
supportsMechanismStrike / priceDetail
[14]
DGEC — Ministère de la Transition écologique (via CRE)2024-04◆ Cahier des charges AO6 (deux installatio…
“5.1 Contrat de Complément de Rémunération 5.1.1 Conclusion du Contrat Après la désignation du Lauréat et avant la Date Effective de Mise en Service, le Producteur est tenu de conclure avec le Cocontra…”
supportsMechanismDetail
Auction results1
[15]
CRE (Commission de regulation de l'energie) / DGEC2024◆ fr-ao6-cahier-des-charges
AO6 cahier des charges ("FLOTTANTES DE MEDITERRANEE") - two floating farms in the Golfe du Lion.
supportsTender award · France Offshore Wind AO6 (Mediterranean floating)
Trade press4
[5]
offshoreWIND.biz2025-09-30
Press report — cited, not quoted; read it at the source link.
supportsStatusConnection pointfabrication
[7]
[8]
[9]