Dieppe-Le Treport

AO2 Round 2 project. Located 17 km from Dieppe and 15.5 km from Le Treport, covering 110 km2.

Delivery outlook modelled by Hafrok · calibrated on delivered projects

Near certainHafrok's delivery likelihood for Dieppe-Le Treport
The developer says 2026. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

4 dated milestones on the spine, each with its source · 5 recorded ownership deals from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 19 sources (17 primary) · ◆ 12 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Operator14
[1]
Eoliennes en Mer Dieppe Le Treport (EMDT)2026-06◆ Le parc éolien en mer de Dieppe Le Trépo…
“La construction est en cours. La mise en service est prévue pour fin 2026. Concrètement, fin 2026, 62 éoliennes d'une puissance de 8 MW chacune produiront de l'électricité grâce à l'énergie du vent. S…”
supportsownerOffshore constructionTurbinesUnit capacityTotal capacity+1 more
[2]
Ocean Winds2023-04-26◆ Dieppe Le Tréport offshore wind farm rea…
“Ocean Winds, Sumitomo Corporation, and la Banque des Territoires as shareholders of the company 'Eoliennes en Mer Dieppe Le Treport' (EMDT) ... The EMDT project represents an investment of around EUR …”
supportsFinal investment decisionCommercial operationTurbinesTotal capacity
[3]
Eoliennes en Mer Dieppe Le Treport (EMDT)2019-02-26
“Les préfets de la région Normandie, de la Seine-Maritime et de la Somme ont autorisé, par arrêtés du 26 février 2019, la réalisation du parc éolien en mer au large de Dieppe et du Tréport et de son ra…”
supportsConsentConsent granted
[4]
Légifrance / Préfet de Seine-Maritime2018-10-12
“Arrêté du 12 octobre 2018 autorisant la société Eoliennes en Mer de Dieppe-Le Tréport (EMDT) à exploiter une installation de production d'électricité ... d'une puissance de 496 MW ... dans le domaine …”
supportsConsentTotal capacityConsent granted
[5]
Ministère de la Transition écologique (France)2023◆ Eolien en mer — French government offsho…
“Les lauréats des appels d'offres éolien en mer signent un contrat d'achat avec EDF Obligation d'Achat (EDF OA) pour une durée de 20 ans, à un tarif fixé lors de l'appel d'offres.”
supportsMechanismDetail
[8]
Nexans2026-02-03
“Nexans has officially handed over both 225 kV HVAC export cable circuits of the Dieppe–Le Tréport offshore wind farm to its client RTE (Réseau de Transport d'Électricité). This milestone marks the for…”
supportsStatusConnection point
[9]
Eoliennes en Mer Dieppe Le Treport (EMDT)2026-06
“Janvier – Fevrier 2024 ... Ces travaux consistent en la pose de granulat en deux couches aux emplacements destinés à accueillir les pieux des fondations. Installation des pieux Juin – decembre 2024 ..…”
supportsturbine assemblyfoundation storageoperations base
[11]
Ocean Winds2025-09-10◆ Ocean Winds celebrates the successful in…
“Ocean Winds celebrates the successful installation of the first jacket foundation at the Dieppe – Le Tréport offshore wind farm. The foundations were loaded at the Port of Cherbourg and installed by D…”
supportsFoundationturbine assemblyfoundation storageoperations base
[15]
DGEC — Ministère de la Transition écologique (eoliennesenmer.fr)2026-08-25◆ French Eoliennes en mer register (DGEC),…
“Register node 852 (node--type-project) at /facades-maritimes-en-france/facade-manche-mer-du-nord/dieppe-le-treport — title 'Dieppe-Le Tréport'; page text 1904 chars, hash e75e5e396a5d093e…. Identifyin…”
supportsRegister entry
[17]
RTE2022-06◆ RTE - Raccordement du parc eolien en mer…
“Depuis le parc éolien en mer, RTE construira une liaison double de 225 000 volts sous-marine (23 km) puis souterraine (3,5 km), pour acheminer l'électricité jusqu'au futur poste électrique dénommé Gra…”
supportsStatusConnection point
[18]
RTE2026-04-14◆ RTE - Dieppe-Le Treport: le raccordement…
“En moins de quatre ans, RTE a construit le raccordement comprenant le poste électrique 225 000 / 400 000 volts de Grande Sole, à Petit-Caux, ainsi qu'une double liaison souterraine et sous-marine 225 …”
supportsStatusConnection point
[20]
Jan De Nul2026-09-11◆ Offshore wind farm dieppe le treport hal…
“This week, our jack-up installation vessel Vole au vent installed the 31st wind turbine at the French offshore wind farm Dieppe-Le Tréport, marking the halfway point of the installation campaign. Sinc…”
supportsStatus note
[21]
Eoliennes en Mer Dieppe Le Tréport (EMDT)2026-06-15◆ Communiqué de presse : Parc éolien en me…
“La première des 62 éoliennes qui composeront le parc éolien en mer de Dieppe Le Tréport a été installée avec succès le 11 juin 2026 ... La SG 8.0-167 de Siemens-Gamesa, est arrivée sur le pont du navi…”
supportsModel
[22]
Eoliennes en Mer Dieppe Le Tréport (EMDT)2026-10-15◆ Parc éolien en mer Dieppe Le Tréport (ho…
“Où en est l'installation en mer aujourd'hui ? La sous-station électrique en mer a été installée en juillet 2025, marquant une étape majeure pour le parc. ... L'installation des fondations est terminée…”
supportsFirst power
Auction results1
[23]
CRE (Commission de regulation de l'energie) / DGEC2013◆ fr-ao2-cahier-des-charges
AO2 cahier des charges (18 Feb 2013): Lot 1 Le Treport 500 MW, Lot 2 Yeu-Noirmoutier 500 MW.
supportsTender award · France Offshore Wind Round 2 (AO2)
Trade press4
[6]
Offshore Wind Biz2025-09-10
Press report — cited, not quoted; read it at the source link.
supportsTurbinesUnit capacityTotal capacityFoundationturbine assembly+2 more
[7]
Offshore Wind Biz2025-07-02
Press report — cited, not quoted; read it at the source link.
supportsDistance from shoreCoordinates
[12]
Power Technology (GlobalData)2022-06◆ Dieppe-Le Treport Offshore Wind Farm
Press report — cited, not quoted; read it at the source link.
supportsWater depth
[14]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.