Pingtan Offshore Area A

Pingtan Offshore Area A is an offshore wind farm in the Taiwan Strait, China, owned by China Energy Engineering Group, in advanced development.

Status
Advanced Developmentlifecycle stage
LikelyHafrok delivery likelihood
Ownership
CEChina Energy Engineering Group — 100% ◇
Location
China
Taiwan Strait
Technology
Capacity 450 MW ◆ Turbines 29 × 16 MW ◇ Foundation Fixed-bottom (structure not recorded) ◇
Site & conditions
Site rights Seabed rights held 2023-05 ◆ Water depth 6–21 m ≈ Wind speed 10.6 m/s @ 150 m ≈
Revenue & grid
Offtake —
Grid —
Schedule
FID Not taken
COD · announced Oct 2028 ◇
COD · Hafrok for registered readers

Delivery outlook modelled by Hafrok · calibrated on delivered projects

LikelyHafrok's delivery likelihood for Pingtan Offshore Area A
The developer says Oct 2028. Hafrok's year agrees with that date; the year, the chance and the working are for registered readers.
Free for registered readers in early access · register below ↓

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

1 dated milestone on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 8 sources (2 primary) · ◆ 6 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator1
[6]
福建省发展和改革委员会 (Fujian Provincial Development and Reform Commission)2025-05-30◆ 福建省发展和改革委员会关于同意平潭A区海上风电场项目核准延期的批复
“我委于2023年5月31日以闽发改网审能源函〔2023〕53号文核准批复了平潭A区海上风电场项目(项目编码:2304-350000-04-01-471371)。 ... 同意该项目核准文件有效期延长1年。 项目其余事项仍按闽发改网审能源函〔2023〕53号文执行,项目核准只能延期一次,期限最长不得超过1年,届时若仍未开工建设,该核准文件自动失效”
supportsConsentSite rightsConsent granted
Operator1
[7]
中国能源建设股份有限公司 (China Energy Engineering Corporation)2023-06-07◆ 中国能源建设股份有限公司 总部新闻 中国能建投资的首个海上风电项目获核准
“装机规模为450兆瓦 ... 拟同步建设一座海上220千伏升压站及一座陆上集控中心”
supportsTotal capacity
Auction pipeline1
[8]
gdshe.org (relaying 北极星风力发电网)2024-07◆ cn-gx2024-launch
广西北海海上风电竞争性配置…N场址…规划容量570万千瓦,P场址规划容量80万千瓦 (~6,500 MW deep-sea), ~94-120 km offshore, 15-45 m depth.
supportsGuangxi Beihai Deep-Sea Offshore Wind Competitive Allocation (广西深远海竞配)
Trade press5
[1]
Global Energy Monitor2026◆ Fujian Pingtan offshore area A wind farm…
supportsownerTotal capacityFoundationCoordinates
[2]
GEBCO Compilation Group2020
supportsWater depth
[3]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[4]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] These turbines are mounted directly onto the sea floor. Offshore floating: ar…”
supportsFoundation
[5]
国际风能网 (International Wind Power Network)2026-05-13◆ 66亿!福建464MW海上风电项目8月开工,拟装29台16MW大风机
Copyrighted source — cited, not quoted; read it at the source link.
supportsFirst powerCommercial operationTurbinesUnit capacity
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.