Huadian Yangjiang Qingzhou III
Located in Shaba, Yangxi, Yangjiang, Guangdong.
Technology
Capacity
503 MW ◇
Turbines
—
Foundation
Fixed-bottom (structure not recorded) ◇
Site & conditions
Site rights
Seabed rights held ∴
Water depth
22–25 m ≈
Wind speed
7.7 m/s @ 100 m ≈
Revenue & grid
Offtake
—
Grid
Not recorded ◇
Connection
Yangjiang 220 kV offshore substation to Shaba onshore substation ◇
Schedule
FID
Taken · date not recorded ∴
COD
2022 ◇
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
3 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 8 sources (2 primary) · ◆ 3 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[4]
Guangdong Provincial Department of Ecology and Environment (广东省生态环境厅)2020-07-13
“经审查,《报告书》基本符合环境保护有关法律法规的要求,在《报告书》提出的各项污染防治对策、生态保护措施和应急措施得到落实的前提下,工程建设对环境产生的不利影响可得到减缓,从海洋环境保护的角度考虑,工程建设可行。我厅同意批准该《报告书》。(粤环审〔2020〕141号,2020年7月13日)”
supportsConsentConsent granted
[6]
NEA Electric Power Reliability Management and Engineering Quality Supervision Center (国家能源局电力可靠性管理和工程质量监督中心)2023-03
“2023年3月24日至25日,可再生能源质监站主要负责同志带队,对华电阳江青洲三海上风电场项目进行质量监督回访。该项目装机容量为500MW,于2021年12月31日全容量并网投产,是已建成的大型海上风电项目中离岸最远、水深最深、施工难度最大、建设工期最短的项目。”
supportsFinal investment decisionCommercial operation
Trade press5
[2]
GEM2026◆ Guangdong Yangjiang Qingzhou III Offshor…
“Guangdong Yangjiang Qingzhou III Offshore wind farm is an operating wind farm in Shaba, Yangxi, Yangjiang, Guangdong, China.”
supportsoperatorCommercial operationTotal capacityStatusConnection point+1 more
[3]
[5]
Yangjiang Radio and Television (阳江视听网)2021-01-04
“2020年12月29日,广东华电阳江青洲三50万千瓦海上风电项目打响沉桩第一锤,标志着我国首个离岸最远、水深最深、单机容量及总装机规模最大的海上风电项目正式进入施工阶段。”
supportsOffshore constructionSite rights
[7]
[8]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] These turbines are mounted directly onto the sea floor. Offshore floating: ar…”
supportsFoundation
Unverified import1
[1]
unknown◆ Guangdong Yangjiang Qingzhou III Offshor…
supportsTotal capacityFoundationWater depthCoordinates