Guangdong Nan'ao Lemen 2

Guangdong Nan'ao Lemen 2. GEM records phase 1 406 MW (2023) operating.

Status
Operationallifecycle stage
Ownership
HGHuaneng Guangdong Shantou Offshore Wind Power ◆
Location
China
Taiwan Strait
Technology
Capacity 594 MW ◆ Turbines 54 × 11 MW ◆ Foundation Fixed-bottom (structure not recorded) ◆
Site & conditions
Site rights Seabed rights held ∴
Revenue & grid
Offtake —
Grid —
Schedule
FID Taken · date not recorded ∴ COD 2023 ◇

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

2 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 4 sources · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[3]
广东省人民政府门户网站 (Guangdong Provincial Government Portal)2023-01-13◆ 华能汕头勒门(二)海上风电场项目完成首桩施工
“1月12日凌晨5时,华能汕头勒门(二)海上风电场项目顺利完成了首根7号风机基础钢管桩沉桩施工, 标志着粤东海域在建单体容量最大的风电场拉开施工序幕。本次施工的7号风机基础钢管桩桩长94.3米, 桩径8米至9米,总重达1802吨。勒门(二)海上风电项目位于南澳岛南侧海域,建设规模59.4万千瓦, 将安装54台11兆瓦风电机组,总投资约82亿元,计划2023年9月份前全容量并网。 [EN] At 05…”
supportsConstruction startSite rightsTurbinesUnit capacityTotal capacity+1 more
[4]
广东省生态环境厅 (Guangdong Provincial Department of Ecology and Environment)2022-10-21◆ 拟对华能汕头勒门(二)海上风电场项目环境影响评价文件作出批准决定的公示
“广东省生态环境厅拟对华能汕头勒门(二)海上风电场项目环境影响评价文件作出批准决定的公示。 建设单位:华能广东汕头海上风电有限责任公司。…我厅拟对该项目环境影响评价文件作出批准决定… 公示期为2022年10月21日至2022年10月27日(5个工作日)。 [EN] Guangdong DEE notice of intent to issue an approval decision on the …”
supportsoperator
Trade press2
[1]
Global Energy Monitor2026◆ Guangdong Nan'ao Lemen 2 Offshore wind f…
supportsConsentFinal investment decisionCommercial operationTotal capacityFoundation+1 more
[2]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] Offshore floating: are an emerging technology designed for installation in de…”
supportsFoundation
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.