Guangdong Nan'ao Lemen 2
Guangdong Nan'ao Lemen 2. GEM records phase 1 406 MW (2023) operating.
Status
Operationallifecycle stage
Ownership
HGHuaneng Guangdong Shantou Offshore Wind Power ◆
Location
Taiwan Strait
Technology
Capacity
594 MW ◆
Turbines
54 × 11 MW ◆
Foundation
Fixed-bottom (structure not recorded) ◆
Site & conditions
Site rights
Seabed rights held ∴
Revenue & grid
Offtake
—
Grid
—
Schedule
FID
Taken · date not recorded ∴
COD
2023 ◇
Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record
2 dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓
Revenue & offtake contract terms, price levels and the route to market
the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓
Installation how the build is going · from sourced statements and Hafrok's registers
construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓
Sources & verification
Rests on 4 sources · ◆ 4 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[3]
广东省人民政府门户网站 (Guangdong Provincial Government Portal)2023-01-13◆ 华能汕头勒门(二)海上风电场项目完成首桩施工
“1月12日凌晨5时,华能汕头勒门(二)海上风电场项目顺利完成了首根7号风机基础钢管桩沉桩施工, 标志着粤东海域在建单体容量最大的风电场拉开施工序幕。本次施工的7号风机基础钢管桩桩长94.3米, 桩径8米至9米,总重达1802吨。勒门(二)海上风电项目位于南澳岛南侧海域,建设规模59.4万千瓦, 将安装54台11兆瓦风电机组,总投资约82亿元,计划2023年9月份前全容量并网。 [EN] At 05…”
supportsConstruction startSite rightsTurbinesUnit capacityTotal capacity+1 more
[4]
广东省生态环境厅 (Guangdong Provincial Department of Ecology and Environment)2022-10-21◆ 拟对华能汕头勒门(二)海上风电场项目环境影响评价文件作出批准决定的公示
“广东省生态环境厅拟对华能汕头勒门(二)海上风电场项目环境影响评价文件作出批准决定的公示。 建设单位:华能广东汕头海上风电有限责任公司。…我厅拟对该项目环境影响评价文件作出批准决定… 公示期为2022年10月21日至2022年10月27日(5个工作日)。 [EN] Guangdong DEE notice of intent to issue an approval decision on the …”
supportsoperator
Trade press2
[1]
Global Energy Monitor2026◆ Guangdong Nan'ao Lemen 2 Offshore wind f…
supportsConsentFinal investment decisionCommercial operationTotal capacityFoundation+1 more
[2]
Global Energy Monitor◆ Global Wind Power Tracker Methodology
“Offshore hard mount: have wind turbines that are usually designed for installation in water no deeper than 60 meters [...] Offshore floating: are an emerging technology designed for installation in de…”
supportsFoundation