Água Marinha

Announced Atlantic-coast complex, sponsor undisclosed.

Status
On Holdlifecycle stage
Ownership
BDBlueFloat Energy do Brasil Ltda — 100% ◆
BLBlueFloat Energy — split undisclosed ◆
Location
Brazil
Southwest Atlantic
Technology
Capacity 1,700 MW ◇
Turbines —
Foundation —
Site & conditions
Site rights Application filed Environmental licence application · 2022-01 ◆ Water depth 1–17 m ≈ Wind speed 9.4 m/s @ 150 m ≈
Revenue & grid
Offtake —
Grid —
Schedule
FID Not taken
COD —
On hold since date not stated ◆

Project timeline & ownership verified milestones on the spine · ownership from Hafrok's transactions record

the dated milestones on the spine, each with its source · the ownership chain from Hafrok's transactions record · the developer's announced-COD history
For registered readers · register below ↓

Revenue & offtake contract terms, price levels and the route to market

the contract terms on record · price over time in money of the day · the routes to market and the next visible round
For registered readers · register below ↓

Installation how the build is going · from sourced statements and Hafrok's registers

construction status and turbines standing · vessel and port contracts · the grid connection and whether it is ready in time
For registered readers · register below ↓

Sources & verification

Rests on 7 sources · ◆ 3 documents held
◆Verified≈Modelled◇Sourced∴Inferred⌁Convention○Unverified∅No source·Derived
Numbers are stable citation ids — grouped by source class, so they are not consecutive.
Regulator2
[5]
IBAMA (Diretoria de Licenciamento Ambiental)2025-03-10◆ Complexos Eolicos Offshore - projetos co…
“Table 'Complexos Eolicos Offshore - projetos com processo de licenciamento ambiental tramitando no Ibama' (atualizado em 10/03/2025): RN-06 - Agua Marinha. Empreendedor: BLUEFLOAT ENERGY DO BRASIL LTD…”
supportsoperatorSite rights
[6]
IBAMA (Diretoria de Licenciamento Ambiental)2026-02-27◆ Complexos Eolicos Offshore - projetos co…
“'COMPLEXOS EOLICOS OFFSHORE - PROJETOS COM PROCESSO DE LICENCIAMENTO AMBIENTAL TRAMITANDO NO IBAMA - Atualizado em 27/02/2026' (59 dockets. 134.255 MW). [Docket RN-06 - Agua Marinha (processo 02001.00…”
supportsOn hold
Trade press5
[1]
GEM2025
supportsTotal capacity
[2]
GEM2025
supportsCoordinates
[3]
GEBCO Compilation Group2020
supportsWater depth
[4]
DTU Wind Energy / World Bank (Global Wind Atlas)2026
supportsMean wind speed
[7]
Offshore Wind (offshorewind.biz)2022-05-04◆ BlueFloat Energy Has 14 Offshore Wind Pr…
Press report — cited, not quoted; read it at the source link.
supports↳ parents
Early access

Follow the offshore wind projects that matter to you.

Hafrok's data and analysis. Free while in early access.

  • The data, in full: the project database as an Excel workbook, Hafrok's expected delivery outlook on every project still to build, the full project records, the transaction database and the developer profiles
  • Hafrok Monitor: follow projects, developers or countries, and Hafrok Monitor mails you what moved on your list, with the source and the date: every Monday morning, or as it happens
  • Hafrok Commentary: analysis of the offshore wind market, when there is something to say
Register, free.

Name and email, no password. Everything listed here opens across the site.

Registering includes news on the projects you follow (Hafrok Monitor), notices about your account, and the occasional question from me about how Hafrok works for you. Switch the Monitor off on your account page, or unsubscribe from any mail with one click. Privacy.