Source: https://hafrok.com/projects/uk-rampion-2/  
Data as of: 2026-10-13

Extension to 400MW Rampion 1 wind farm off Sussex coast.

| Field | Value |
|---|---|
| Country | United Kingdom |
| Sea basin | English Channel |
| Capacity | 1200 MW |
| Turbines | 90 |
| Lifecycle stage | Advanced Development |
| Owners | RWE · Macquarie · Enbridge |
| Commercial operation (developer guidance, convention year) | 2030 |
| Commercial operation (Hafrok's expected year) | 2032 (range 2031–2033) |
| Chance of delivery | Expected (weight 0.729) |

## Milestones

- **Consent applied** — 2023-08-10 (achieved)
- **Consent granted** — 2025-04-28 (achieved)
- **Commercial operation** — 2032 (expected)

## Offtake

No offtake secured — route to market open


## Sources

Every figure above traces to one of these. Quoted passages are held but not republished; follow the link for the original wording.

- RWE AG, 2025-04-04 — https://www.rwe.com/en/press/rwe-offshore-wind-gmbh/2025-04-04-uk-government-gives-green-light-to-rampion/
- Planning Inspectorate, 2025-04-04 — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010117
- HMSO / Planning Act 2008, 2025-04-04 — https://www.legislation.gov.uk/uksi/2025/468/introduction/made
- DESNZ / GOV.UK, 2025-04-04 — https://www.gov.uk/government/news/rampion-2-offshore-wind-farm-development-consent-decision-announced
- RWE AG, 2021-01-18 — https://www.rwe.com/en/press/rwe-renewables/2021-01-18-rampion-2-wind-farm-extension-opens-informal-consultation/
- Offshore Wind Biz, 2020-09-28 — https://www.offshorewind.biz/2020/09/28/rwe-signs-lease-agreements-for-four-uk-offshore-wind-extensions/
- Rampion Extension Development Ltd / RWE, 2025-09 — https://rampion2.com/the-project/
- RWE AG (UK), 2025 — https://uk.rwe.com/project-proposals/rampion-2/
- Rampion Extension Development Ltd / RWE, 2025-09 — https://rampion2.com/newsletter/september-2025/
- DTU Wind Energy / World Bank (Global Wind Atlas), 2026 — https://globalwindatlas.info/
- Department for Energy Security and Net Zero, 2026-05-06 — https://assets.publishing.service.gov.uk/media/69fc56908cc72d2f863ea58d/REPD_publication_Q1_2026.csv
- National Energy System Operator (NESO), 2026-07-21 — https://api.neso.energy/dataset/cbd45e54-e6e2-4a38-99f1-8de6fd96d7c1/resource/17becbab-e3e8-473f-b303-3806f43a6a10/download/tec-register-21-july-2026.csv
- The Planning Inspectorate (PINS), 2026-08-23 — https://national-infrastructure-consenting.planninginspectorate.gov.uk/api/applications-download
- DESNZ (gov.uk), 2026 — https://www.gov.uk/government/collections/contracts-for-difference-cfd-allocation-round-8

---

Hafrok · https://hafrok.com/projects/uk-rampion-2/ · please cite the page you took a figure from.