title: "Baltyk 2"
source: https://hafrok.com/projects/pl-baltyk-2/
identifier: pl-baltyk-2
updated: 2026-10-13
---

# Baltyk 2

Source: https://hafrok.com/projects/pl-baltyk-2/  
Data as of: 2026-10-13

Twin project with Baltyk 3, combined 1,440 MW. Located off Ustka coast. Landfall via horizontal directional drilling near Ustka.

| Field | Value |
|---|---|
| Country | Poland |
| Sea basin | Baltic Sea |
| Capacity | 720 MW |
| Turbines | 50 |
| Lifecycle stage | Under Construction |
| Owners | Equinor · Polenergia |
| Coordinates | 55.0801, 16.88 |
| Commercial operation (announced) | 2028 |
| Commercial operation (Hafrok's expected year) | 2028 (range 2027–2028) |
| Chance of delivery | Delivering (weight 0.979) |

## Milestones

- **Consent applied** — 2024-03-27 (achieved)
- **Consent granted** — 2024-08 (achieved)
- **Final investment decision** — 2025-05 (achieved)
- **Onshore construction** — 2025-06 (achieved)
- **Offshore construction** — 2026-01 (achieved)
- **Commercial operation** — 2028 (expected)

## Offtake

720 MW contracted — tender award

- **Tender award · Poland offshore CfD Phase 1 (administrative)** — 319.6 PLN/MWh · awarded 2021-06 · 25-year term

## Sources

Every figure above traces to one of these. Quoted passages are held but not republished; follow the link for the original wording.

- Equinor, 2025-05-22 — https://www.equinor.com/news/20250522-financial-close-for-baltyk-2-and-baltyk-3
- Polenergia, 2025-05-19 — https://www.polenergia.pl/en/equinor-and-polenergia-take-final-investment-decisions-fids-for-baltyk-2-and-baltyk-3-offshore-wind-projects/
- Polenergia, 2025-05-23 — https://www.polenergia.pl/en/largest-project-finance-transaction-in-polands-energy-industry-history-equinor-and-polenergia-reach-financial-close-for-each-of-the-baltyk-2-and-baltyk-3-projects/
- Equinor, 2021-05-04 — https://www.equinor.com/news/archive/20210412-breakthrough-polish-wind
- European Commission, 2021-05 — https://ec.europa.eu/commission/presscorner/detail/en/ip_21_2567
- Equinor, 2022-02-22 — https://www.equinor.com/news/archive/202202-baltyk-turbine-supplier
- Sif Holding N.V., 2024-02-16 — https://sif-group.com/newsroom/baltyk-iiiii-final/
- European Investment Bank, 2025-05-23 — https://www.eib.org/en/press/all/2025-217-eib-extends-eur700-million-for-development-of-two-major-new-offshore-wind-farms-in-poland
- offshoreWIND.biz, 2025-06-30 — https://www.offshorewind.biz/2025/06/30/equinor-and-polenergias-baltyk-2-3-offshore-wind-farms-enter-construction-phase/
- offshoreWIND.biz, 2024-08-22 — https://www.offshorewind.biz/2024/08/22/all-construction-permits-granted-for-baltyk-2-baltyk-3-offshore-wind-farms-in-poland/
- offshoreWIND.biz, 2024-07-11 — https://www.offshorewind.biz/2024/07/11/polish-govt-clears-720-mw-offshore-wind-farm-for-construction/
- offshoreWIND.biz, 2026-02-18 — https://www.offshorewind.biz/2026/02/18/offshore-construction-starts-on-polish-baltyk-2-3-wind-farms/
- NS Energy Business, 2025-01 — https://www.nsenergybusiness.com/projects/mfw-baltyk-ii-and-mfw-baltyk-iii-wind-farms/
- Global Energy Monitor, 2026-07-02 — https://www.gem.wiki/Ba%C5%82tyk_2_Offshore_wind_farm
- DTU Wind Energy / World Bank (Global Wind Atlas), 2026 — https://globalwindatlas.info/
- Polenergia, 2026-04-29 — https://www.polenergia.pl/en/the-baltyk-2-and-baltyk-3-offshore-wind-farms-are-growing-fast-both-onshore-and-offshore/
- Polenergia, 2026-05-25 — https://www.polenergia.pl/en/kick-off-of-offshore-installation-the-first-foundations-installed-at-baltyk-2-3/
- Polenergia, 2026-07-14 — https://www.polenergia.pl/en/landfall-hdd-completed-for-the-baltyk-2-3-export-cables/
- Polenergia, 2026-07-01 — https://www.polenergia.pl/en/baltyk-2-3-turbine-foundations-halfway-complete/
- Polenergia S.A., 2024-02-16 — https://www.polenergia.pl/en/siemens-gamesa-to-supply-baltyk-ii-and-baltyk-iii-projects-with-their-largest-offshore-wind-turbines-to-date/
- Heerema Marine Contractors, 2026-09-02 — https://heerema.com/news/heerema-marine-contractors-installs-100-turbine-foundations-2-oss-jackets-at-ba%C5%82tyk-2-3-offshore-wind-farm
- Polenergia S.A., 2025-05-19 — https://www.polenergia.pl/raporty_biezace/podjecie-ostatecznych-decyzji-inwestycyjnych-dotyczacych-realizacji-projektow-morskich-farm-wiatrowych-fid/
- Polenergia S.A., 2025-05-19 — https://www.polenergia.pl/en/raporty_biezace/making-final-investment-decisions-on-the-implementation-of-offshore-wind-farm-projects-fid/
- Polenergia S.A., 2026-05 — https://www.polenergia.pl/wp-content/uploads/2026/05/SkonsolidowanyraportkwartalnyzaIkwartal2026roku.pdf
- Sejm / ISAP, 2021 — https://isap.sejm.gov.pl/isap.nsf/download.xsp/WDU20210000234/O/D20210234.pdf
- Polenergia, 2026-09-02 — https://www.polenergia.pl/baltyk-2-i-3-z-kompletem-fundamentow/
- Norton Rose Fulbright, 2026-06-22 — https://www.nortonrosefulbright.com/en/knowledge/publications/009c7a09/global-offshore-wind-poland

---

Hafrok · https://hafrok.com/projects/pl-baltyk-2/ · please cite the page you took a figure from.