Located off Choczewo/Leba coast. Onshore substation at Choczewo municipality complete and ready for commissioning tests.

| Field | Value |
|---|---|
| Country | Poland |
| Sea basin | Baltic Sea |
| Capacity | 1140 MW |
| Turbines | 76 |
| Lifecycle stage | Under Construction |
| Owners | ORLEN · Northland Power |
| Coordinates | 55.05, 17.65 |
| Commercial operation (announced) | 2026 |
| Commercial operation (Hafrok's expected year) | 2026 (range 2025–2026) |
| Chance of delivery | Delivering (weight 0.977) |

## Milestones

- **Onshore construction** — 2023 (achieved)
- **Consent granted** — 2023-08-16 (achieved)
- **Final investment decision** — 2023-10 (achieved)
- **Offshore construction** — 2025-01 (achieved)
- **First power** — 2026-07 (achieved)
- **Commercial operation** — 2026 (expected)

## Offtake

1,197 MW contracted — tender award

- **Tender award · Poland offshore CfD Phase 1 (administrative)** — 319.6 PLN/MWh · awarded 2021-06 · 25-year term

## Sources

Every figure above traces to one of these. Quoted passages are held but not republished; follow the link for the original wording.

- Baltic Power (ORLEN Group / Northland Power), date not stated — https://balticpower.pl/about-the-project/
- Vestas / windfair, 2023-09-28 — https://w3.windfair.net/wind-energy/news/45590-vestas-wind-turbine-offshore-order-poland-baltic-power-baltic-sea-service-agreement-mw
- Baltic Power (ORLEN Group / Northland Power), 2024-10-18 — https://balticpower.pl/news/first-monopiles-for-baltic-power-offshore-wind-farm-ready-for-shipment/
- The Wind Power (industry database), date not stated — https://www.thewindpower.net/windfarm_en_24033_baltic-power.php
- Energy Regulatory Office (URE) / offshoreWIND.biz, 2021-06-16 — https://www.offshorewind.biz/2021/06/16/1-2-gw-baltic-power-offshore-wind-farm-secures-contract-for-difference/
- Baltic Power (ORLEN Group), 2021-01-14 — https://balticpower.pl/news/orlen-secures-grid-connection-agreement-for-its-offshore-wind-farm/
- Northland Power, 2023-09-19 — https://www.northlandpower.com/en/news/northland-power-announces-signing-of-credit-agreement-for-52-billion-project-financing-at-baltic-pow.aspx
- ORLEN (Grupa ORLEN), 2023-10-12 — https://www.energyglobal.com/wind/12102023/orlen-embarks-on-construction-of-central-europes-largest-green-energy-project/
- ORLEN (Grupa ORLEN), 2026-02-18 — https://www.orlen.pl/en/about-the-company/media/press-releases/current/2026/february-2026/All-foundations-installed-as-Baltic-Power-moves-closer-to-completion
- Baltic Power (ORLEN Group / Northland Power), 2025-11-01 — https://balticpower.pl/news/baltic-power-opens-poland-s-first-offshore-wind-service-base/
- Baltic Power (ORLEN Group), 2025-02-05 — https://balticpower.pl/news/baltic-powers-offshore-substation-structures-have-left-the-port-of-gdynia-they-are-now-sailing-for-outfitting/
- ORLEN, 2026-06 — https://www.orlen.pl/en/about-the-company/media/press-releases/current/2026/June-2026
- offshoreWIND.biz, 2023-05-23 — https://www.offshorewind.biz/2023/05/23/baltic-power-onshore-substation-work-kicks-off/
- Baltic Power (ORLEN Group / Northland Power), 2025-02-06 — https://balticpower.pl/news/first-foundations-at-the-baltic-power-offshore-farm-installed/
- DTU Wind Energy / World Bank (Global Wind Atlas), 2026 — https://globalwindatlas.info/
- Northland Power, 2026-07-10 — https://northlandpower.com/northlands-baltic-power-reaches-first-power-delivering-first-offshore-wind-electricity-to-polands-grid/
- Northland Power, 2025-07-07 — https://northlandpower.com/baltic-power-offshore-wind-farm-installs-its-first-turbine-in-poland/
- Baltic Power, 2026-06-08 — https://balticpower.pl/aktualnosci/baltic-power-zabezpiecza-kluczowe-kontrakty-na-faz%C4%99-eksploatacji-pierwszej-polskiej-morskiej-farmy-wiatrowej/
- Baltic Power, 2026-06-08 — https://balticpower.pl/aktualnosci/baltic-power-zabezpiecza-kluczowe-kontrakty-na-faz%C4%99-eksploatacji-pierwszej-polskiej-morskiej-farmy-wiatrowej/
- Baltic Power, 2026-06-08 — https://balticpower.pl/aktualnosci/baltic-power-zabezpiecza-kluczowe-kontrakty-na-faz%C4%99-eksploatacji-pierwszej-polskiej-morskiej-farmy-wiatrowej/
- Baltic Power, 2026-06-08 — https://balticpower.pl/aktualnosci/baltic-power-zabezpiecza-kluczowe-kontrakty-na-faz%C4%99-eksploatacji-pierwszej-polskiej-morskiej-farmy-wiatrowej/
- Baltic Power, 2026-03-19 — https://balticpower.pl/aktualnosci/wszystkie-elementy-przej%C5%9Bciowe-%C5%82%C4%85cz%C4%85ce-fundamenty-z-turbinami-i-morskimi-stacjami-elektroenergetycznymi-zainstalowane-na-morskiej-farmie-wiatrowej-baltic-power/
- Baltic Power, 2026-07-10 — https://balticpower.pl/aktualnosci/morska-farma-wiatrowa-baltic-power-po-raz-pierwszy-wyprodukowa%C5%82a-i-dostarczy%C5%82a-energi%C4%99-z-morza-dla-polskiej-sieci-energetycznej/
- Baltic Power, 2025-11-13 — https://balticpower.pl/aktualnosci/pierwsze-gondole-morskich-turbin-wiatrowych-z-polskiej-fabryki-zosta%C5%82y-zainstalowane-na-farmie-wiatrowej-baltic-power/
- Baltic Power, 2026-06-22 — https://balticpower.pl/aktualnosci/ju%C5%BC-50-turbin-zainstalowanych-na-morskiej-farmie-wiatrowej-baltic-power-wkr%C3%B3tce-start-kluczowych-test%C3%B3w/
- Vestas Wind Systems A/S, 2022-09-26 — https://www.vestas.com/en/media/company-news/2022/vestas-selected-as-preferred-supplier-for-the-1-2-gw-ba-c3636425
- Vestas Wind Systems A/S, 2023-09-28 — https://www.vestas.com/en/media/company-news/2023/vestas-wins-1-140-mw-offshore-order-for-v236-15-0-mw-wi-c3844196
- Northland Power, 2026-08-12 — https://northlandpower.com/northland-power-reports-second-quarter-2026-results-and-construction-progress-updates/
- Baltic Power, 2026-10-07 — https://balticpower.pl/aktualnosci/wszystkie-76-turbiny-na-baltic-power-zainstalowane-pierwsza-polska-morska-farma-wiatrowa-wchodzi-w-ko%C5%84cow%C4%85-faz%C4%99-rozruch%C3%B3w-przed-startem-komercyjnej-eksploatacji/
- Northland Power, 2026-10-07 — https://northlandpower.com/northlands-baltic-power-offshore-wind-project-completes-installation-of-all-76-turbines/
- Ministry of Climate and Environment (Ministerstwo Klimatu i Środowiska), 2026-10-07 — https://www.gov.pl/web/klimat/pierwsza-polska-morska-farma-wiatrowa-ukonczona
- Cadeler, 2026-10-07 — https://www.cadeler.com/news/cadeler-completes-its-turbine-installation-campaign-at-baltic-power-polands-first-offshore-wind-farm
- Wojewoda Pomorski (Pomorski Urząd Wojewódzki w Gdańsku), 2025-11-27 — https://www.gov.pl/attachment/d8d0fc0a-4d78-44aa-aff2-a0dfba83f23f
- Norton Rose Fulbright, 2026-06-22 — https://www.nortonrosefulbright.com/en/knowledge/publications/009c7a09/global-offshore-wind-poland
- Van Oord, 2025-02 — https://www.vanoord.com/en/updates/heavy-lift-installation-vessel-svanen-installs-first-monopile-baltic-power-wind-farm/
- offshore-energy.biz / offshoreWIND.biz, 2026-03-20 — https://www.offshorewind.biz/2026/03/20/all-transition-pieces-in-place-at-baltic-power-offshore-wind-farm/
- Cadeler A/S, 2025-07-07 — https://www.cadeler.com/news/first-successful-wtg-installation-at-baltic-power-offshore-wind-farm
- Cadeler A/S, 2026-04-10 — https://www.cadeler.com/news/wind-mover-has-started-her-first-project-following-delivery

---

Hafrok · https://hafrok.com/projects/pl-baltic-power/ · please cite the page you took a figure from.