# IJmuiden Ver Beta Phase 1 (Zeevonk)

Source: https://hafrok.com/projects/nl-ijmuiden-ver-beta-phase-1-zeevonk/  
Data as of: 2026-10-13

Zeevonk consortium originally planned 2 GW + 50 MW floating solar + 1 GW electrolyser at Maasvlakte.

| Field | Value |
|---|---|
| Country | Netherlands |
| Sea basin | North Sea |
| Capacity | 1000 MW |
| Lifecycle stage | Advanced Development |
| Owners | Vattenfall · Copenhagen Infrastructure Partners |
| Coordinates | 52.944, 3.518 |
| Commercial operation (announced) | 2030 |
| Commercial operation (Hafrok's expected year) | 2032 (range 2031–2033) |
| Chance of delivery | Expected (weight 0.824) |

## Milestones

- **Consent granted** — 2024-06-11 (achieved)
- **Consent applied** — 2024-Q1 (achieved)
- **Commercial operation** — 2032 (expected)

## Offtake

No offtake secured — route to market open


## Sources

Every figure above traces to one of these. Quoted passages are held but not republished; follow the link for the original wording.

- unknown, date not stated — https://www.offshorewind.biz/2025/08/11/vattenfall-cip-dutch-offshore-wind-farm-delayed-to-2032-project-to-be-built-in-two-phases/
- unknown, date not stated — https://group.vattenfall.com/press-and-media/pressreleases/2024/vattenfall-and-copenhagen-infrastructure-partners-awarded-ijmuiden-ver-beta-offshore-wind-farm
- unknown, date not stated — https://renews.biz/102384/dutch-approve-ijmuiden-ver-beta-delay-to-2032/
- RVO (Netherlands Enterprise Agency), 2024-06-11 — https://english.rvo.nl/news/permit-results-ijmuiden-ver-alpha-en-beta
- RVO (Netherlands Enterprise Agency), 2025-10 — https://english.rvo.nl/subsidies-financing/offshore-wind-energy/ijmuiden-ver
- WindpowerNL, 2025-08-08 — https://windpowernl.com/2025/08/08/dutch-government-amends-offshore-wind-permit-for-ijmuiden-ver-beta-project-due-to-delta-rhine-corridor-delay/
- Offshore Wind Biz, 2024-12-18 — https://www.offshorewind.biz/2024/12/18/google-buys-offshore-wind-power-from-vattenfall-cip-jv/
- RVO (Netherlands Enterprise Agency), 2023-11 — https://offshorewind.rvo.nl/file/download/e0d69fb9-a3a4-48b5-b106-3f0928239b56/ijv_20231122_psd-alpha-and-beta_final-version.pdf
- offshoreWIND.biz, 2025-08 — https://www.offshorewind.biz/2025/08/11/vattenfall-cip-dutch-offshore-wind-farm-delayed-to-2032-project-to-be-built-in-two-phases/
- 4C Offshore, 2026-07-02 — https://www.4coffshore.com/windfarms/ijmuiden-ver-beta-netherlands-nl0s.html
- GEBCO Compilation Group, 2020 — https://www.gebco.net/data_and_products/gridded_bathymetry_data/
- DTU Wind Energy / World Bank (Global Wind Atlas), 2026 — https://globalwindatlas.info/
- Vattenfall, 2026-07-17 — https://group.vattenfall.com/siteassets/corporate/investors/interim_reports/2026/vattenfall-q2-presentation-2026.pdf
- Vattenfall, 2025-Q3 — https://group.vattenfall.com/siteassets/corporate/investors/interim_reports/2025/q3-report-2025.pdf
- RVO — Bureau Energieprojecten (energietransitie.nl), 2026-08-23 — https://energietransitie.nl/energieprojecten
- DEME, 2026-07-20 — https://www.deme-group.com/news/deme-awarded-contract-foundation-installation-zeevonk-offshore-wind-farm-netherlands
- RVO, 2026 — https://english.rvo.nl/news/tender-opens-offshore-wind-farm-2026
- Vattenfall, 2026-07-20 — https://group.vattenfall.com/press-and-media/newsroom/2026/vattenfall-and-copenhagen-infrastructure-partners-award-deme-contract-for-foundation-installation-at-zeevonk-offshore-wind-farm
- offshore-energy.biz / offshoreWIND.biz, 2026-08-31 — https://www.offshorewind.biz/2026/08/31/jacket-for-tennets-ijmuiden-ver-beta-platform-starts-taking-shape/

---