BNetzA auction result June 2024. Offshore Wind One GmbH (TotalEnergies) bid EUR 1.305 million/MW. Grid connection target end of 2030.

| Field | Value |
|---|---|
| Country | Germany |
| Sea basin | North Sea |
| Capacity | 1500 MW |
| Lifecycle stage | Early Development |
| Owners | TotalEnergies |
| Coordinates | 54.856, 6.377 |
| Commercial operation (announced) | 2032 |
| Commercial operation (Hafrok's expected year) | 2034 (range 2034–2042) |
| Chance of delivery | Prospective (weight 0.59) |

## Milestones

- **Consent applied** — 2026-06-11 (achieved)
- **Commercial operation** — 2034 (expected)

## Offtake

No offtake secured — route to market open


## Sources

Every figure above traces to one of these. Quoted passages are held but not republished; follow the link for the original wording.

- unknown, date not stated — https://www.power-technology.com/news/bp-totalenergies-german-offshore-wind/
- Bundesnetzagentur, 2024-06-13 — https://www.bundesnetzagentur.de/SharedDocs/Pressemitteilungen/EN/2024/20240613_BK6_Offshore.html
- TotalEnergies, 2024-06-24 — https://totalenergies.com/news/press-releases/germany-totalenergies-wins-further-maritime-lease-north-sea-develop-15-gw
- offshoreWIND.biz, 2024-06-24 — https://www.offshorewind.biz/2024/06/24/enbw-totalenergies-win-in-2-5-gw-german-offshore-wind-auction-as-rwe-bows-out/
- Baltic Wind, 2024-10-14 — https://balticwind.eu/totalenergies-renames-key-german-offshore-wind-projects/
- TotalEnergies Germany, 2026-06-11 — https://totalenergies.de/ueber-uns/presse/pressemitteilungen/TotalEnergies-bekr%C3%A4ftigt-sein-Engagement-f%C3%BCr-den-Ausbau-der-Offshore-Windenergie-in-Deutschland
- BSH (Bundesamt fuer Seeschifffahrt und Hydrographie), 2025-05 — https://wp.bsh.de/en/blog/2025/05/15/site-development-plan-2025-decision-on-the-route-of-the-offshore-grid-connection-systems-nor-11-1-nor-11-2-nor-12-1-nor-12-2-and-nor-13-1/
- offshoreWIND.biz, 2024-06 — https://www.offshorewind.biz/2024/06/24/enbw-totalenergies-win-in-2-5-gw-german-offshore-wind-auction-as-rwe-bows-out/
- TotalEnergies, 2024 — https://totalenergies.com/news/press-releases/germany-totalenergies-wins-further-maritime-lease-north-sea-develop-15-gw
- 4C Offshore, 2026-07-02 — https://www.tgs4c.com/windfarms/germany/n-11.2-germany-de3o.html
- GEBCO Compilation Group, 2020 — https://www.gebco.net/data_and_products/gridded_bathymetry_data/
- DTU Wind Energy / World Bank (Global Wind Atlas), 2026 — https://globalwindatlas.info/
- Bundesnetzagentur, 2026 — https://www.bundesnetzagentur.de/DE/Beschlusskammern/BK06/BK6_72_Offshore/Ausschr_nicht_zentral_vorunters_Flaechen/start.html

---