Guangdong Xuwen Donger. GEM records phase 1 300 MW (2026) construction.

| Field | Value |
|---|---|
| Country | China |
| Sea basin | South China Sea |
| Capacity | 300 MW |
| Lifecycle stage | Under Construction |
| Owners | Xinhua Longyuan (Xuwen) New Energy |
| Coordinates | 20.5755, 110.4451 |
| Commercial operation (Hafrok's expected year) | 2028 (range 2027–2029) |
| Chance of delivery | Delivering (weight 0.967) |

## Milestones

- **Offshore construction** — 2026-09-04 (achieved)
- **Commercial operation** — 2028 (expected)

## Offtake

Offtake regime not on record


## Sources

Every figure above traces to one of these. Quoted passages are held but not republished; follow the link for the original wording.

- Global Energy Monitor, 2026 — https://www.gem.wiki/Guangdong_Xuwen_Donger_Offshore_wind_farm
- Global Energy Monitor, date not stated — https://www.gem.wiki/Global_Wind_Power_Tracker_Methodology
- 羊城派 (via 21经济网), 2026-09-06 — https://www.21jingji.com/article/20260906/herald/6b02ac88b4840ed91205ffeb9430edf6.html

---