Guangdong Coastal Test Site Single. GEM records phase 1 18 MW (2024) operating.

| Field | Value |
|---|---|
| Country | China |
| Sea basin | South China Sea |
| Capacity | 18 MW |
| Lifecycle stage | Operational |
| Coordinates | 23.3576, 116.8224 |
| Commercial operation (announced) | 2024 |

## Milestones

- **Commercial operation** — 2024 (achieved)

## Offtake

Offtake regime of the vintage — not a recorded contract


## Sources

Every figure above traces to one of these. Quoted passages are held but not republished; follow the link for the original wording.

- Global Energy Monitor, 2026 — https://www.gem.wiki/Guangdong_Coastal_Test_Site_Single_Offshore_wind_farm
- Global Energy Monitor, date not stated — https://www.gem.wiki/Global_Wind_Power_Tracker_Methodology
- 国家发展和改革委员会 (NDRC), 2021-06-07 — https://www.ndrc.gov.cn/xxgk/zcfb/tz/202106/t20210611_1283088_ext.html

---